400KV TRANSMISSION DEVELOPMENT (2009-2013), 400KV CABLE CIVIL WORKS PACKAGE (B)

Client:
EWA

Consultant:
Mott Macdonald

Location:
Riffa To Um Al Hassam To Hidd, BAHRAIN                 

 

Brief Description:

Civil Works as S/C Package to Prysmian Group for the 400kV circuit from the new Riffa S/S to the new Um Al Hassam S/S and from Um Al Hassam to Hidd (Feeder 1). Riffa to Um al Hassam is referred to as Stage 1 & the other Stage 2.

Scope of Works:

The scope of works include surveys, soil investigation, route clearance, temporary works, site offices and lay down areas, excavations, conventional road crossings ducts, non-disruptive road and sea crossings, concrete works, cable installation in precast concrete Troughs generally, backfilling (Thermal & normal) and reinstatement, all associated with the installation of the 400kV single circuit.