Link road in-between Gulf of Bahrain Road with Al Sahel Development. Approximately 10.0 km new road will be constructed as a dual two-lane carriageway with associated stormwater drainage and other utility works (Package-A: 4,700m)
The Scope of works consisting of the following:
? 4700m Road Works (2 Lanes Dual Carriageway)
? Road Marking and Signage Work
? Drainage Works (Storm Water Line 3,760m)
? TSE Line (5,000m)
? Street Lighting and Miscellaneous Works
? 8m Deep Pumping Station including MEP
? 3 Nos. Culvert and 1 No. Outfall
? Safety Barriers (Concrete and TCB)